Listed building consent for air conditioning: cost, time and how to apply
Listed building consent costs nothing to apply for, but a listed home also needs planning permission for an outdoor unit, and a thin application is the quickest way to a refusal. This guide takes you through the process in order: checking the list entry, getting early advice, what to submit and who prepares it, fees, timescales, conditions, appeals and what happens if work goes ahead first.
to apply for listed building consent £0

- to apply for listed building consent
- £0
- planning fee from 1 April 2026
- £548
- to decide, once valid
- 8 weeks
- to start work after consent
- 3 years
On this page15 sections
What you're applying for
Listed building consent is the authorisation section 7 of the Planning (Listed Buildings and Conservation Areas) Act 1990 requires before anyone alters a listed building 'in any manner which would affect its character as a building of special architectural or historic interest'.
- Does air conditioning need it? Historic England's view is that air conditioning is likely to, and heat pumps fixed to a building normally do. Our guide to air conditioning in a listed building explains why.
- Planning permission too: listed homes and their gardens have no permitted development right for heat pumps.
- Two decisions, one submission: Historic England says they should be considered at the same time, and there's a combined householder planning and listed building consent form for England.
- In practice you make one submission with one set of drawings.
- Consent is for the works, not for you. It stays with the property, and whoever carries out the works must follow it and its conditions.
The process, step by step
Find the list entry
Search the National Heritage List for England by address or map. Note the seven-figure list entry number, the grade, the date first listed and any parts the entry excludes. Remember the whole building, inside and out, is listed, however short the description.
Survey and options
Before anything is drawn, work out where the outdoor unit, pipes and indoor units could go and which positions do least harm. Record the alternatives and why you rejected them: Historic England says it should be clear why less harmful options were discounted.
Get early advice
Historic England recommends talking to the council's conservation officer early. Councils offer an informal view, sometimes free, or paid pre-application advice. In Bath, for example, a conservation officer site visit for listed building energy works costs £76 from 1 April 2026.
Prepare the documents
Scaled drawings, product and sound data, photos, a design and access statement, a statement of significance and a method statement. The checklist below lists each one.
Submit both applications
Apply online through the Planning Portal or direct to the council. Listed building consent is free; the planning fee is £548 for a house or a single flat from 1 April 2026. The council checks the application is valid before the clock starts.
Decision and conditions
The council has 8 weeks from a valid application. Consent usually comes with conditions, some of which must be cleared before work starts.
Install as approved
Start within 3 years unless the consent says otherwise, follow the approved drawings exactly, and keep the decision notices with your deeds for when you sell.
What to submit for an air conditioning or heat pump install
National requirements plus what Historic England and councils ask for with plant on listed buildings. Your council's local validation list may add items.
- The application form and the right ownership certificate: Certificate A if you own the freehold outright, Certificate B with notice served on other owners, such as a freeholder
- A location plan at 1:1250 or 1:2500 on up-to-date mapping, with the property edged in red
- A block or site plan at 1:200 or 1:500 showing boundaries, neighbours and the unit position
- Existing and proposed elevations of every affected wall at 1:50 or 1:100, with written dimensions and a scale bar
- Existing and proposed floor plans showing each indoor unit, the pipe, cable and condensate routes, and every wall opening
- Details of how the outdoor unit and any screen are fixed, and how they could be removed later
- Product data: dimensions, colour, sound power level, and efficiency figures
- Photos of each elevation and room affected, with the proposed positions marked; a photomontage helps for sensitive positions
- A design and access statement, which every listed building consent application needs
- A statement of the building's significance and the effect of the works, in proportion to the job
- A method statement and schedule of works: fixings, core holes, pipe routes, making good and protecting finishes
- The case for the system: the heating benefit, the simple cooling measures already in place and why rooms still overheat
- Noise evidence: the maker's data and an MCS 020 calculation, plus an acoustician's report if your council asks for one
Who usually prepares each document
You can write and submit an application yourself. Most people use specialists for some parts.
| Document | Usually prepared by | What we provide |
|---|---|---|
| Forms and ownership certificate | You, or an agent you appoint | Help completing the form; we can submit as your agent if you ask |
| Location and block plans | Whoever draws the scheme, on licensed Ordnance Survey mapping | Included in the design pack |
| Plans, elevations, fixing and pipe route drawings | The installer's designer, an architect or a surveyor | Included in the design pack, from our measured survey |
| Product, sound and efficiency data | The installer, from the manufacturer | Included, with our MCS 020 calculation |
| Design and access statement | You or your agent, with technical input | The technical text: positions, fixings, removal, routes |
| Statement of significance | You, where the council accepts it, or a heritage consultant | Not ours to write; we can introduce independent consultants |
| Acoustic report, where asked for | An acoustician (IOA or ANC member) | Not ours to write; we supply the unit data and positions they need |
Historic England's Advice Note 18 says the information should be proportionate to the impact, and asks for a statement by an appropriately qualified specialist for major cases. Ask the conservation officer what yours needs.
What it costs
The fees paid to the council, and the costs you may meet around them. Read October 2026.
| Item | Cost | Notes |
|---|---|---|
| Listed building consent application | No fee | No current fee in England, on the Planning Portal schedule |
| Householder planning permission | £548 | From 1 April 2026, for one house. A single flat is also £548 |
| Certificate of Lawfulness of Proposed Works | No fee | Rarely suits a full install; see below |
| Online submission | Service charge may apply | The Planning Portal adds a charge to some applications; it shows at checkout |
| Pre-application advice | Set by each council | Free informal views at some councils; Bath's conservation officer visit is £76 |
| Acoustician's report | About £400 to £600 | Only where the council asks for one |
| Appeal against a refusal | No fee | For listed building consent appeals, on gov.uk |
| Our design pack | From £795 | Taken off your installation if you go ahead with us |
How long listed building consent takes
The council has 8 weeks to decide a listed building consent application, counted from when it has the valid application and certificate. Householder planning applications have the same 8-week period.
- The clock starts at validation, so missing documents add time before the 8 weeks even begin.
- **Grade I or II*:** the council must notify Historic England of every application.
- Amenity societies, such as the Georgian Group and the Victorian Society, are notified where works include demolishing any part of a listed building.
- Whether a core hole counts isn't settled in the rules, and councils differ.
- Plan ahead: allow for preparing the documents and getting pre-application advice on top of the 8 weeks.
- Consent lasts 3 years. Under section 18 of the 1990 Act, works must begin within 3 years of the date of consent unless the council sets a different period.
- If you don't start in time, you have to apply again.
Conditions, and clearing them
Most consents come with conditions. Historic England's Advice Note 16 says they may require a schedule of works, a method statement, or details of new services. For air conditioning that often means the exact unit model and colour, the screen design, fixing details or a noise limit at the neighbour's window.
Read the decision notice carefully. Some conditions must be cleared before any work starts, by sending the council the details it asked for and waiting for written approval. Failing to comply with a listed building consent condition is itself an offence under section 9(2), so we don't start until every pre-start condition has been discharged.
The certificate of lawfulness route
Since 6 April 2014 you can ask the council for a Certificate of Lawfulness of Proposed Works under section 26H of the 1990 Act. It confirms that works would not affect the building's special interest, so need no consent.
- The terms: it's free, it lasts 10 years, and it can't be applied for after the work is done.
- It doesn't remove the need for planning permission.
- Rarely succeeds for a new install, because Historic England's starting point is that air conditioning is likely to affect special interest.
- Worth trying in narrow cases: a like-for-like replacement on an existing consented position and pipe route.
- Or an install entirely within a part of the building the list entry excludes.
- Or a modern extension with no special interest where every pipe runs through modern fabric.
If consent is refused
Read the reasons first. Published guidance points to the usual ones: a position visible from the street, harm to historic fabric from fixings or pipe runs, too many units, or noise.
- Reapply with changes: a different position, a ground frame instead of a wall bracket, one multi-split outdoor unit instead of two, or a screen can turn a refusal into a consent.
- Or appeal to the Planning Inspectorate.
- Listed building consent appeals: 6 months from the decision, or from when it was due if you didn't get one within 8 weeks. There's no fee, and only the applicant can appeal.
- Householder planning appeals: 12 weeks from the decision letter.
- Because an outdoor unit needs both, appeal both within 12 weeks so they are heard together.
Retrospective listed building consent
If a unit has already gone up without consent, the council can grant consent to keep it under section 8(3) of the 1990 Act. But the works are only authorised from the date of that consent.
- It doesn't undo the offence committed when they were done, and the council judges the application exactly as it would have beforehand.
- If it's refused, the council can serve a listed building enforcement notice under section 38, requiring the building to be put back.
- There is no time limit, and it can be served on a later owner.
- An appeal against the notice must be received before it takes effect.
- Bought a house with an unconsented unit? Take advice before you change or remove anything.
Why applications stall or fail
From council validation guidance and published heritage advice.
| Problem | What to do instead |
|---|---|
| Drawings not to a stated scale, unlabelled, or not matching each other | Number and title every drawing, state the scale at a paper size, and check plans and elevations agree |
| No red line on the location plan | Edge the whole property in red on current Ordnance Survey mapping |
| No design and access statement | Include one: every listed building consent application needs it |
| Unit dimensions or pipe routes missing | Show the unit's size on every drawing and every pipe, inside and out |
| No noise information where the council asks for it | Include the maker's data and calculation, and an acoustic report if your council requires one |
| A heritage statement written after the design was fixed | Start from the building's significance, then design around it |
| Citing a neighbour's unit as precedent | Make the case on your own building; councils say precedent isn't a deciding factor |
Bath's council, with about 5,000 listed buildings in the city, says objections arise 'Where plans and drawings are not of a professional standard, lack detail or are inaccurate'.
Where our design pack helps
The council decides from drawings and technical detail. Our design pack covers that technical side from one measured survey:
- Location and block plans, and existing and proposed plans and elevations
- Fixing and pipe route details, and the equipment schedule
- The maker's sound data and our MCS 020 calculation
- Photos with the positions marked, and the technical text for the design and access statement
- Help with the form, and one round of changes after the officer's comments
- We are air conditioning installers, not architects, heritage consultants or acousticians.
- We don't write the statement of significance or an acoustic report, but we tell you at the start if your council will want them and can introduce independent specialists.
- The council decides, and the fee is payable whether or not consent is granted. Our design pack terms set out the rest.
The design pack fee
From £795, fixed in writing before anything starts. It can be more for a larger home, a Grade I or II* building, or a council that asks for more. It's paid in full when you accept, and taken off your installation if you accept our install quote within 6 months.
- from£795
A design pack for a consent application
Drawings, specification and sound data; taken off the install if you go ahead
Listed building consent questions
Is listed building consent free?
Yes. There is no fee for a listed building consent application in England, or for a Certificate of Lawfulness of Proposed Works. But an outdoor unit at a listed home also needs planning permission, which costs £548 for a householder application from 1 April 2026, and you pay for whatever drawings and reports the council needs.
How much does listed building consent cost for air conditioning?
The application is free. The real costs are the planning fee (£548 from 1 April 2026), any pre-application advice your council charges for, and the drawings. Our design pack starts from £795 and comes off the installation if you go ahead with us. An acoustician's report, where a council asks for one, is usually about £400 to £600.
How long does listed building consent take?
The council has 8 weeks from a valid application. Add the time to prepare the documents, any pre-application advice, and any delay while the council checks the application is valid. For Grade I and II* buildings Historic England is notified and may comment, so start early if you want the system in before summer.
How long does listed building consent last?
Three years. Section 18 of the 1990 Act says the works must begin within 3 years of the date consent is granted, unless the council sets a different period. If you don't start in time it lapses and you have to apply again.
Do I need drawings for listed building consent?
Yes. Every application needs plans to an identified scale, and for air conditioning that means a location plan, a block plan, existing and proposed elevations and floor plans, and details of fixings and pipe routes. Councils refuse or invalidate applications where drawings are inaccurate or missing detail.
Can I apply for listed building consent myself?
Yes. Anyone can prepare and submit an application, and you don't need an architect. What matters is that the drawings meet the council's standards and the statement explains the significance of the building and the effect of the works. Historic England says the information should be proportionate to the impact, so ask the conservation officer whether a statement you write yourself will do for a simple Grade II job.
Can I get retrospective listed building consent?
Yes, under section 8(3), for keeping works already done. But the works are only authorised from the date consent is granted, so it doesn't cancel the offence, and the council can refuse it and serve an enforcement notice requiring removal. There is no time limit on that enforcement.
What happens if my application is refused?
You can change the design and apply again, or appeal. Listed building consent appeals must be made within 6 months and cost nothing; householder planning appeals have 12 weeks. If both were refused, appeal both within 12 weeks. Often a new position, a ground-mounted unit or a single outdoor unit is the quicker route.
Does Historic England decide my application?
No, your council does. Historic England is notified of every application for a Grade I or II* building and may comment. For a Grade II house, a heating and cooling install isn't one of the works it must be told about, so the council's conservation officer usually advises and the council decides.